Perteet delivered the design and construction management services for the 2019 Stormwater Projects for the City of Yakima. The project identified eight distinct sites within the city limits for storm drain improvements to decrease flooding through modular detention takes, swales, and other BMPs. Perteet managed this project from the 30% design level through final contract documents, bidding, and construction completion. During construction, our construction management team documented all the contractor activities, coordinated property restoration, managed design changes, and tracked each site’s progress and schedule. Our team developed and maintained a complete document set for final records for the City, including field note records, daily reports, field directives, submittals, meeting minutes, RFIs, weekly statement of working days, and progress payment applications for the City to process.